250 MW Mandsaur Solar Project has achieved COD in September-2017. 100% power being supplied to Madhya Pradesh Power Management Company Ltd (MPPMCL )from 250 MW Mandsaur project. Evacuation Plan is being divided into 2 phases. Power is being evacuated temporarily through Phase-I connectivity in Suwasra. Phase II work is ongoing which involves providing permanent connectivity of 220 kV transmission line from Suwasra to upcoming 220/400 kV MPPTCL substation in Sitamau, Mandsaur. MPPTCL 220/400 kV substation is expected to be commissioned by March, 2020.